How Long Does G99 Approval Take? What 417 UK Homes Waited

If your solar and battery system has an inverter above 3.68 kW, your network operator has to approve it before it is connected. That is a G99 application. Here is how long approval actually took for 417 Spark homes, by inverter size and over time, and what it means for your install date.

Updated November 2026·7 min read·Written by the Spark team from SparkOS data
An EcoFlow hybrid inverter and battery modules on a house wall, beside its isolator switches
Key takeaways
  • About a week is typical. The median wait from application to approval was 7 days, and half of homes waited between 1 and 21 days.
  • 65% were approved within two weeks and 85% within four.
  • Bigger inverters waited longer. The median was 5 days for 5 kW, 12 days for 6 kW and 21 days for 8 kW and over.
  • More homes now need it. 80% of Spark orders from October had an inverter above 3.68 kW, up from 25% in January to March.

The Short Answer

For Spark customers, G99 approval took a median of 7 days. 65% of homes were approved within two weeks and 85% within four weeks.

You don't have to apply yourself. We send the application to your network operator, usually within 2 days of you signing, and we plan your install day around it. In 409 of 417 homes (98%), approval was in place by install day.

The wait varies. About one home in five was approved the same day we applied, while 11 of 417 waited more than eight weeks. The size of your inverter makes the most difference, as the table below shows.

G98 or G99: Which Applies to You?

Which application you need depends on how much power your system can push into the grid at once, which is set by your inverter.

  • G98 covers systems up to and including 16 amps per phase, which is 3.68 kW on an ordinary single-phase home supply. These follow a simpler process and the network operator paperwork is usually quick.
  • G99 covers anything above that. The network operator has to accept the application before the system is connected.
  • Batteries count. For the quicker G99 route, the total capacity includes electricity storage, not just the solar.
  • Three-phase homes have the 3.68 kW limit on each phase, so a larger inverter can still fall under G98.

These rules come from the Energy Networks Association, which publishes the G98 and G99 standards (ENA: connecting generation to the networks). The ENA says a system on the quicker G99 route can usually be commissioned between 10 working days and three months after the application. Most of our approvals came well inside that.

How Long It Took, by Inverter Size

Every G99 application we made for Spark orders signed from January 2025 that has an approval date: 417 homes.

InverterHomesMedian waitMiddle halfWithin 2 weeksWithin 4 weeks
5 kW1975 days1⁠–⁠14 days78%91%
6 kW19212 days2⁠–⁠27 days55%80%
8 kW and over2821 days6⁠–⁠28 days39%75%

Days from our application to the network operator's approval. "Middle half" is the 25th to 75th percentile.

5 kW systems were usually approved within a week. 6 kW systems took a median of 12 days, and the few homes with 8 kW or more took a median of 21 days, though three-quarters of them were still approved within four weeks. The data shows the difference, not the reason for it. Our sizing guide explains how the inverter is chosen.

Has It Got Quicker?

Yes, for our customers. The median wait was 16 days for applications made in 2025 and 6 days in 2026.

AppliedHomesMedian waitMiddle halfWithin 4 weeks
Jul–Sep 20253021 days9⁠–⁠38 days70%
Oct–Dec 2025227 days3⁠–⁠15 days95%
Jan–Mar 20263815 days4⁠–⁠30 days74%
Apr–Jun 2026966 days0⁠–⁠21 days84%
Jul–Sep 20261565 days1⁠–⁠19 days87%
Oct–Nov 2026705 days1⁠–⁠16 days97%

By the date we applied. Applications before July 2025 are left out: only 5 have an approval date recorded. October–November 2026 runs to 24 November 2026; every application in it had been approved.

Part of the change is the mix of inverters: in 2025 most of our G99 homes had a 6 kW inverter, and in 2026 more had 5 kW. But 6 kW systems got quicker too, from a median of 19 days in 2025 to 8 days in 2026.

Our records don't say why. One change in the industry is ENA Connect Direct, an online service for these applications that can approve some automatically when they pass its checks and passes the rest to an engineer (ENA Connect Direct). We can't tell from our data which approvals came that way, so we don't claim it explains the trend.

Why More Homes Now Need G99

Homes are choosing bigger inverters and batteries, and anything above 3.68 kW needs G99.

Orders signedInverter above 3.68 kWAverage battery
Jan–Mar 202625%8.0 kWh
Apr–Jun 202657%8.9 kWh
Jul–Sep 202671%10.7 kWh
Oct–19 Nov 202680%12.3 kWh

Spark solar and battery orders, from our monthly install data to 19 November 2026.

Across all 558 Spark orders signed from 1 January to 19 November 2026, 59% had an inverter above 3.68 kW. A larger inverter makes sense for bigger systems and batteries, and more homes are choosing bigger batteries. The data shows the shift, not every reason for it. Our monthly install data tracks both, month by month.

Want to know if you need G99?
Your quote shows the inverter size and whether we need to apply. We do the paperwork.
Get My Free Quote

What Spark Does for You

G99 sounds technical, but you don't need to do anything except sign.

  1. We size the inverter. Your quote shows the inverter we recommend, and whether it needs G99.
  2. We apply. We send the application to your network operator, usually within 2 days of you signing.
  3. We handle the questions. If the operator asks for more information, we deal with it.
  4. We book your install around it. We plan your install day around the approval.

If you would rather avoid G99, a 3.68 kW inverter keeps you under the limit. It can suit smaller systems and batteries, and your quote will explain the trade-off.

How It Affects Your Install Date

Approval usually comes well before install day. For the homes in this guide, the median gap between approval and install day was 14 days.

A G99 system still takes longer from signing to install day than one with a 3.68 kW inverter, because there is more to arrange. Our installation time guide sets out how long each inverter size took, from signing to install day.

How We Worked Out These Figures

These figures come from SparkOS, our own operations system.

They cover Spark solar and battery orders signed between 1 January 2025 and 27 November 2026 that had reached the install stage, 1,279 in all. 454 of them needed G99: an inverter above 3.68 kW on a single-phase supply, or above 11.04 kW on three phases. The wait is the number of days from the date we applied to the network operator to the date it approved the connection, as recorded in SparkOS. We left out 23 early-2025 applications with no approval date recorded, 5 with no application date and 9 whose dates were in the wrong order, leaving 417 homes, with applications made between 23 April 2025 and 24 November 2026. "Median" is the 50th percentile and "middle half" the 25th to 75th percentiles. Every group shown has at least 12 homes. The share of orders needing G99 comes from our monthly install data. The figures are as at 27 November 2026.

Frequently asked questions

Your Questions, Answered.

How long does G99 approval take?

For 417 Spark homes, the median was 7 days from application to approval. 65% were approved within two weeks and 85% within four.

What is the difference between G98 and G99?

G98 covers systems up to 16 amps per phase, which is 3.68 kW on a normal single-phase home supply, and has a simpler process. G99 covers bigger systems, which the network operator has to approve before they are connected.

Do I need G99 for a battery?

It depends on the inverter, not the battery alone. If your inverter is above 3.68 kW on a single-phase supply, you need G99, and battery storage counts towards the size of the system.

Who makes the G99 application?

We do. Spark applies to your network operator on your behalf and plans your install day around the approval.

Does G99 cost extra?

A larger inverter adds time rather than cost for the approval itself. We handle the application as part of your installation.